MCQ Questions and Answers 2024 of Software Project Management

BCA Nepal

  1. Which of the following is a people-intensive activity?
    • a) Problem solving
    • b) Organization
    • c) Motivation
    • d) Project management
    Answer: d) Project management
  2. Software ____ provides the framework from which a comprehensive plan for software development can be established.
    • a) People
    • b) Product
    • c) Process
    • d) None of the above
    Answer: c) Process
  3. Which of the following is an important factor that can affect the accuracy and efficacy of estimates?
    • a) Project size
    • b) Planning process
    • c) Project complexity
    • d) Degree of structural uncertainty
    Answer: b) Planning process
  4. The critical path method is good for
    • a) Small project
    • b) Large project
    • c) Both small and large
    • d) Medium project only
    Answer: c) Both small and large
  5. A ____ is developed using historical cost information that relates some software metric to the project cost.
    • a) Algorithmic cost modeling
    • b) Expert judgment
    • c) Estimation by analogy
    • d) Parkinson’s Law
    Answer: a) Algorithmic cost modeling
  6. Which of the following are parameters involved in computing the total cost of a software development project?
    • a) Hardware and software costs
    • b) Effort costs
    • c) Travel and training costs
    • d) All of the above
    Answer: d) All of the above
  7. Which of the following is a project scheduling method that can be applied to software development?
    • a) PERT
    • b) CPM
    • c) CMM
    • d) Both PERT and CPM
    Answer: d) Both PERT and CPM
  8. One of the following is a Risk management responsibility.
    • a) Project team
    • b) Investor
    • c) Developer
    • d) Customer
    Answer: a) Project team
  9. Inspections and testing are what kinds of Quality Costs?
    • a) Prevention
    • b) Internal Failure
    • c) External Failure
    • d) Appraisal
    Answer: d) Appraisal
  10. Who plays the role of policy maker in change management?
    • a) Project manager
    • b) Customer
    • c) SCM manager
    • d) None of the above
    Answer: a) Project manager

The answers are:

  1. d
  2. c
  3. b
  4. c
  5. a
  6. d
  7. d
  8. a
  9. d
  10. a
PREVIOUS POSTNEXT POST